Designer promised to deliver a logo package by March 1. The contract did not state that time was of the essence. On March 3, before Client hired anyone else or lost a campaign deadline, Designer delivered the complete logo package and offered to credit Client for the two-day delay. Client rejected the delivery solely because it was late.
Which statement is most accurate?